:::FotoCap 1: View looking at the exterior stucco on the south elevation from Clay Street.







:::FotoCap 2: Close-up view of the west elevation from Clay Street.








:::FotoCap 3: Close-up view of the decks on the west elevation.






Observations:::

From this week's drive-by, work continues on the exterior decks. Brick veneer is being applied to the column locations and the scratch coat of gray stucco is being placed on the west elevation. Finished stucco is mostly complete on the south elevation. The rest of the building is still being covered with plastic wrap.