Wednesday, February 13, 2008

February 13th


:::FotoCap 1: View looking at the exterior stucco on the south elevation from Clay Street.







:::FotoCap 2: Close-up view of the decks from Clay Street.








:::FotoCap 3: View of the east elevation from River Street.






Observations:::

Another drive-by this week. Brick veneer continues to be applied to the upper column locations. Finished stucco has begun on the west elevation setbacks and deck ceilings. Finished stucco work continues on the upper floors of the south elevation. Brick veneer continues on the east elevation as well. Celloluse insulation continues to be fed into the Third Level.

:::Weekly Slice of RiverClay PAN