Thursday, February 28, 2008

February 27th


:::FotoCap 1: View looking at Unit Plan 'M' Living Room.








:::FotoCap 2: View looking at Unit Plan 'M' Kitchen.








:::FotoCap 3: View looking at Unit Plan 'D' Kitchen.








:::FotoCap 4: View looking at Unit Plan 'D' Master Bath.








:::FotoCap 5: View looking at Unit Plan 'D' Master Closet.








:::FotoCap 6: View looking at Unit Plan 'C' Kitchen.








:::FotoCap 7: View looking at Unit Plan 'C' Master Bath.








:::FotoCap 8: View looking at Unit Plan 'J' Kitchen.








:::FotoCap 9: View looking at the photovoltaic panel installation on the Roof Level.





Observations:::
Very exciting news from this week's site walk: Work continues on the exterior stucco and brick columns. On the interior, individual unit finishes are being installed on the 2nd Floor which includes kitchen cabinets and countertops, bathroom cabinets and fixtures, and closet doors. On the 3rd Floor, drywall is almost done and being prepped for unit finishes to begin. On the Upper Floors, wall insulation and drywall are progressing. On the Roof Level, photovoltaic panels are being installed along the west and east sides.

:::No Weekly Slice of RiverClay PAN this week

Wednesday, February 13, 2008

February 13th


:::FotoCap 1: View looking at the exterior stucco on the south elevation from Clay Street.







:::FotoCap 2: Close-up view of the decks from Clay Street.








:::FotoCap 3: View of the east elevation from River Street.






Observations:::

Another drive-by this week. Brick veneer continues to be applied to the upper column locations. Finished stucco has begun on the west elevation setbacks and deck ceilings. Finished stucco work continues on the upper floors of the south elevation. Brick veneer continues on the east elevation as well. Celloluse insulation continues to be fed into the Third Level.

:::Weekly Slice of RiverClay PAN

Monday, February 4, 2008

January 30th


:::FotoCap 1: View looking at the exterior stucco on the south elevation from Clay Street.







:::FotoCap 2: Close-up view of the west elevation from Clay Street.








:::FotoCap 3: Close-up view of the decks on the west elevation.






Observations:::

From this week's drive-by, work continues on the exterior decks. Brick veneer is being applied to the column locations and the scratch coat of gray stucco is being placed on the west elevation. Finished stucco is mostly complete on the south elevation. The rest of the building is still being covered with plastic wrap.

:::Weekly Slice of RiverClay PAN