:::FotoCap 1: View from the corner of River and Clay Streets.









:::FotoCap 2: View of the northwest turret.










:::FotoCap 3: View from Clay Street looking at the 3rd and 4th Floor decks.







:::FotoCap 4: View looking at the south side.






Observations:::

First things first,... GO ROCKIES!!
This week, I report as the building is about 1/2 topped out at the Roof Level. The 6th Floor is about 1/2 exterior sheathed and 1/2 wood framed. The CMU stair towers at the north and south sides are close to topping out too. Steel framing and railing is being erected for the 3rd and 4th Floor decks on the east and west sides. Exterior windows are being installed around the 3rd Floor. More brick continues to be laid along the west side of the 1st Floor. A HUGE RiverClay.com sign has been displayed along the south side.

:::Weekly Slice of RiverClay PAN