Photo taken from ground level at the northwest corner - my unit is on the far left, northeast corner, three floors up.

The lower level north stair and elevator cores have been poured. Formwork is being assembled for the south cores. Rebar continues to be placed for the interior columns. The west foundation wall is mostly complete. Foundation drainage board and dampproofing have been applied around the north exterior wall.