Wednesday, July 25, 2007
July 25th
:::FotoCap : View from Clay Street, looking north at the southwest corner of RiverClay
The second floor slab pour is underway. The concrete pumper truck is working on the south end of the building. Column rebar is being placed on the north end. The stationary crane is at the central east end of the building site. Clay Street remains open to one lane of traffic.